Lookout Substation Construction Project

Type: Substation
Scope: Constructed a greenfeild 138kV substation and subsurface cabling.
Location: Garland, Texas

Client: Garland Power & Light

Garland Power & Light (“GPL”) is a not-for-profit municipal utility serving nearly 71,000 customers in and around the city of Garland, Texas. In May 2016, GPL contracted Irby to construct the greenfield 138kV Lookout substation. The project scope included all surfacing, grounding, structure erection, bus/equipment installation, cable trenching, conduit systems, testing, and substation site restoration. Irby was assisted by American Site Builders for foundations and footings construction. The project was completed on schedule and to budget in November 2016.

Start Date: May 2016
Completion Date: November 2016

 

If you would like to request information on this project or submit a request for bid, click here.