FPL EVolution HUB

FPL EVolution HUB

FPL EVolution HUB

Type: Substation and Renewable
Scope: Construct a Microgrid Grid
(Solar Farm, BESS, and EV Charging Stations)
Location: Riviera Beach, Florida
Client: Florida Power & Light

Irby was awarded the construction of the Florida Power and Light (FPL) EVolution Hub project in August 2021. This innovative microgrid (energy storage project) comprises a 5-MW solar array and a 7.5-MW by 15-MWh stationary battery, as well as two mobile EV trailers. The two, 28-foot mobile EV charging stations, built by our affiliate company Brink Construction, will be able to provide clean energy on the go. The mobile EV trailers will each carry a fully charged battery. The EV chargers will be stationed at FPL’s West Palm Beach service facility, where EV fleet drivers can charge their vehicles. EV charging trailers will help during public emergencies or in evacuation situations, such as hurricanes.

The project will enable FPL to test the design and benefits of movable EV charging stations and gain further insight into microgrid technology.

Irby’s full scope of construction includes site civil and access work, complete solar farm installation incorporating foundations, modules, racking, collection systems, conduit installation, and commissioning of all components of the microgrid. Working with FPL Construction managers, Irby will complete this project by mid-year 2022.

Start Date: August 2021
Scheduled Completion: March 2022

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Sunshine Gateway Battery Energy Storage Center

Sunshine Gateway Battery Energy Storage Center

Sunshine Gateway Energy Storage Center

Type: Substation, Renewable
Scope: Construct a new battery energy storage center
Location: Columbia County, Florida
Client: Florida Power & Light

Irby was awarded the construction of the Florida Light & Power (FPL) Sunshine Gateway Battery Energy Storage Center (BESS) in August of 2020. The 30MW battery storage facility consists of 10 new battery line-ups (battery containers and integrated inverter/pad-mount transformer skids) connected to an adjacent 230/34.5 kV substation. The work includes, but is not limited to, the installation of all civil works, including the BESS pad, drainage infrastructure, roads, foundations, conduits, grounding, structures, equipment, batteries, and battery enclosures, control building, cabling, and testing.

The battery storage system is fed by the FPL Sunshine Gateway Solar Energy Center, a 74.5 MW facility sitting on over 900 acres located near the intersection of I-10 and I-75. The solar plant generates zero-emissions for FPL customers and generates enough renewable energy to power approximately 15,000 Florida homes. Operation of this renewable source is the equivalent of removing 12,000 cars from the road each year.

Local ABC affiliate, 20 WCJB ran a softy on the project. Watch it here. https://www.wcjb.com/content/news/FPL-opens-new-solar-energy-power-plant-in-Columbia-County-506341811.html

Start Date: March 2021
Completion Date: In Progress/Scheduled December 2021

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Manatee Battery Energy Storage Center

Manatee Battery Energy Storage Center

Manatee Battery Energy Storage Center

Type: Substation, Renewable
Scope: Construct a new battery energy storage center
Location: Manatee County, FL​
Client: Florida Power & Light

Irby was awarded the construction of the Florida Light & Power (FPL) Manatee Battery Energy Storage Center (BESS) in August of 2020. The BESS and substation consist of 132 new battery line-ups (battery containers and integrated inverter/pad-mount transformer skids), connected to a new 230/34.5 kV substation. The substation consists of 44 feeder breakers, each connected to three battery line-ups; four bus-tie breakers; six transmission breakers; two charging feeder breakers; three GSUs; and associated other equipment, bus, cables, conduit, grounding, foundations, etc.

This 409MW/900MWh energy storage center, the equivalent of 100 million iPhone batteries, will be the world’s largest solar-powered battery. The project will accelerate the retirement of fossil fuel generation, saving FPL customers more than $100 million while eliminating more than 1 million tons of carbon dioxide emissions. 

“Irby has worked with FPL for over 20 years. However, this is the first project of this kind together and unique in scope,” said Andre Foster, Vice President of Business Development and Major Projects. “Irby looks forward to completing this special project with a long-standing partner like FPL.” 

Start Date: September 2020
Completion Date: In Progress/Scheduled December 2021 

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Comanche Solar 34.5/230kV Substation and Transmission Line Construction Project

Comanche Solar 34.5/230kV Substation and Transmission Line Construction Project

Comanche Solar 34.5/230kV Substation and Transmission Line Construction Project

Type: Substation
Scope: Constructed a 34.5/230kV substation, a 2.5 mile 34.5kV interconnection, and an underground 230kV transmission line.
Location: Pueblo, Colorado

Client: CG Power Solutions USA

Online since 2016, Xcel Energy’s (“Xcel”) 120MW Comanche Solar project is the largest solar project east of the Rockies (~3.5 megaton carbon offset), generating enough energy to power more than 31,000 homes. Under EPC contract with Xcel, CG Power USA Inc. (“CGP”) subcontracted Irby in December 2015 to construct a 34.5/230kV substation for the project including a 2.5 mile 34.5kV interconnection between the east and west solar fields and a 230kV underground transmission line from the substation to Xcel’s Comanche Generation Station. The Irby work scope was completed in under six months with zero lost time incidents.

Start Date: December 2015
Completion Date: May 2016

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Gray-Allen Creek 345kV Transmission Line Construction Project

Gray-Allen Creek 345kV Transmission Line Construction Project

Gray-Allen Creek 345kV Transmission Line Construction Project

Type: Renewables, Transmission
Scope: Constructed 25 miles of 345kV transmission line in support of a North Texas wind project.
Location: Pampa, Texas

Client: Cross Texas Transmission

Founded in 2008, Cross Texas Transmission (“CTT”) is a regulated transmission service provider providing energy to wholesale markets across Texas. The bulk of CTT’s capacity derives from its owned and operated network of transmission lines (>320 miles) which delivers wind power from the Texas Panhandle to its customers.

In January 2016, CTT contracted Irby to incorporate power from the Salt Fork Wind project in Gray and Donley Counties by constructing 25 miles of 345kV transmission line. The Irby work scope included the installation of steel structures, foundations, and wire operations. Irby was assisted by Aldridge Construction (direct embed drilling and structure setting), Winco Powerline (lead-in installation and diverters), and B&M Telecom (Fiber splicing). Both Irby and Winco Powerline are Quanta Services subsidiary companies (PWR:NYSE).

The project was completed in August 2016 to schedule and with zero lost-time incidents.

To learn more about this project watch this video.

Start Date: January 2016
Completion Date: August 2016

 

If you would like to request information on this project or submit a request for bid, click here.