FPL EVolution HUB

FPL EVolution HUB

FPL EVolution HUB

Type: Substation and Renewable
Scope: Construct a Microgrid Grid
(Solar Farm, BESS, and EV Charging Stations)
Location: Riviera Beach, Florida
Client: Florida Power & Light

Irby was awarded the construction of the Florida Power and Light (FPL) EVolution Hub project in August 2021. This innovative microgrid (energy storage project) comprises a 5-MW solar array and a 7.5-MW by 15-MWh stationary battery, as well as two mobile EV trailers. The two, 28-foot mobile EV charging stations, built by our affiliate company Brink Construction, will be able to provide clean energy on the go. The mobile EV trailers will each carry a fully charged battery. The EV chargers will be stationed at FPL’s West Palm Beach service facility, where EV fleet drivers can charge their vehicles. EV charging trailers will help during public emergencies or in evacuation situations, such as hurricanes.

The project will enable FPL to test the design and benefits of movable EV charging stations and gain further insight into microgrid technology.

Irby’s full scope of construction includes site civil and access work, complete solar farm installation incorporating foundations, modules, racking, collection systems, conduit installation, and commissioning of all components of the microgrid. Working with FPL Construction managers, Irby will complete this project by mid-year 2022.

Start Date: August 2021
Scheduled Completion: March 2022

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Sunshine Gateway Battery Energy Storage Center

Sunshine Gateway Battery Energy Storage Center

Sunshine Gateway Energy Storage Center

Type: Substation, Renewable
Scope: Construct a new battery energy storage center
Location: Columbia County, Florida
Client: Florida Power & Light

Irby was awarded the construction of the Florida Light & Power (FPL) Sunshine Gateway Battery Energy Storage Center (BESS) in August of 2020. The 30MW battery storage facility consists of 10 new battery line-ups (battery containers and integrated inverter/pad-mount transformer skids) connected to an adjacent 230/34.5 kV substation. The work includes, but is not limited to, the installation of all civil works, including the BESS pad, drainage infrastructure, roads, foundations, conduits, grounding, structures, equipment, batteries, and battery enclosures, control building, cabling, and testing.

The battery storage system is fed by the FPL Sunshine Gateway Solar Energy Center, a 74.5 MW facility sitting on over 900 acres located near the intersection of I-10 and I-75. The solar plant generates zero-emissions for FPL customers and generates enough renewable energy to power approximately 15,000 Florida homes. Operation of this renewable source is the equivalent of removing 12,000 cars from the road each year.

Local ABC affiliate, 20 WCJB ran a softy on the project. Watch it here. https://www.wcjb.com/content/news/FPL-opens-new-solar-energy-power-plant-in-Columbia-County-506341811.html

Start Date: March 2021
Completion Date: In Progress/Scheduled December 2021

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Manatee Battery Energy Storage Center

Manatee Battery Energy Storage Center

Manatee Battery Energy Storage Center

Type: Substation, Renewable
Scope: Construct a new battery energy storage center
Location: Manatee County, FL​
Client: Florida Power & Light

Irby was awarded the construction of the Florida Light & Power (FPL) Manatee Battery Energy Storage Center (BESS) in August of 2020. The BESS and substation consist of 132 new battery line-ups (battery containers and integrated inverter/pad-mount transformer skids), connected to a new 230/34.5 kV substation. The substation consists of 44 feeder breakers, each connected to three battery line-ups; four bus-tie breakers; six transmission breakers; two charging feeder breakers; three GSUs; and associated other equipment, bus, cables, conduit, grounding, foundations, etc.

This 409MW/900MWh energy storage center, the equivalent of 100 million iPhone batteries, will be the world’s largest solar-powered battery. The project will accelerate the retirement of fossil fuel generation, saving FPL customers more than $100 million while eliminating more than 1 million tons of carbon dioxide emissions. 

“Irby has worked with FPL for over 20 years. However, this is the first project of this kind together and unique in scope,” said Andre Foster, Vice President of Business Development and Major Projects. “Irby looks forward to completing this special project with a long-standing partner like FPL.” 

Start Date: September 2020
Completion Date: In Progress/Scheduled December 2021 

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Northeast 138kV Substation Upgrade Project

Northeast 138kV Substation Upgrade Project

Northeast 138kV Substation Upgrade Project

Type: Substation
Scope: 
Performed the demolition and reconstruction of a 138kV substation.
Location: Oolagah, Oklahoma
Client: American Electric Power Oklahoma Transmission Company

American Electric Power Oklahoma Transmission Company (“AEPOT”) (a subsidiary of American Electric Power), contracted Irby in November 2017 to demolish and reconstruct the 22 breaker 138kV Northeastern substation near Oolagah, Oklahoma. The project scope included the installation of two new 138kV bays, the transfer of existing lines, and demolition of the existing substation to phased AEPOT outage cadence. The Northeastern substation provides essential power to the Tulsa metropolitan area and all outages were executed to AEPOT schedule and with zero lost-time incidents.

Start Date: November 2017
Completion Date: November 2019

 

If you would like to request information on this project or submit a request for bid, click here. 

 

Colton Lane Substation Upgrade Project

Colton Lane Substation Upgrade Project

Colton Lane Substation Upgrade Project

Type: Substation
Scope:
Constructed a 3000A capacity substation including installation of 138kV electrical bus work.
Location: Austin, Texas
Client: Lower Colorado River Authority

The Lower Colorado River Authority (“LCRA”) is a non-profit public utility providing water stewardship and energy to more than 70 counties throughout Texas. In July 2018, LCRA contracted Irby to upgrade the capacity of its 138kV Colton Lane Electrical Substation in southeast Travis County, Texas.

Constructed to serve the anticipated load growth of the Bluebonnet Electric Cooperative (Owners of 11,000+ miles of power lines across 14 counties), the Colton Lane substation was successfully upgraded by Irby to its newly rated 3000A capacity within a condensed LCRA schedule and with zero lost time incidents in September 2018.

Start Date: July 2018
Completion Date: September 2018

 

If you would like to request information on this project or submit a request for bid, click here.